Former Hospital Demolition Strategy Open House March 1, 2017

Thu, 16 Feb 2017

Town Hall, Oakville and Trafalgar rooms
1225 Trafalgar Road
March 1, 2017, 6–8 p.m.

The demolition of the former hospital (OTMH) site is scheduled to begin this summer 2017 and take approximately 12 months to complete.The town is committed to safely deconstructing the former hospital and Helen Lawson buildings and has a comprehensive Demolition Strategy to guide the process.

Attend our open house to find out more about the strategy including:

  • performance guidelines
  • abatement and demolition activities
  • mitigations to minimize dust, noise and traffic

The overall demolition approach will be completed using standard mechanical demolition which involves mechanized equipment, articulated lifts and cranes. The demolition of the buildings will use a 3Rs approach – reduce, reuse and recycle – with the contractor diverting as much waste as possible from landfill.

Accessibility requirements

If you have any accessibility needs, please let us know by February 22 by contacting ServiceOakville at 905-845-6601 (TTY: 905-338-4200), email service@oakville.ca, or by filling out the accessible feedback form.

Background

The Oakville-Trafalgar Memorial Hospital (OTMH) site was part of the town’s overall South Central Public Lands Study (SCPLS) — which reviewed a number of key sites, owned by the town, in south central Oakville (e.g. surplus school sites, Oakville Arena) and made recommendations about their future use, including recreation uses. The Former Hospital Site Project is about the town working with our community partners to create a vibrant new community centre, park, and future residential housing to meet the needs of Oakville residents.

For more information

For more information about the Former Hospital Site Project and to sign up for email updates from the town, please visit the Former Hospital Site page. You can also email  formerhospitalsite@oakville.ca or contact ServiceOakville at 905-845-6601.