Bridge Road closure from April 23 to August 10, 2018

Mon, 16 Apr 2018

Bridge Road will be closed from Smith Lane to Lee's Lane from April 16 to August 10, 2018 for Phase Two of the Bridge Road reconstruction project. Work will begin on April 23, 2018.

Motorists will be directed along Fourth Line, Maplehurst Avenue, Pinegrove Road and Lee’s Lane in both directions. Residents will be permitted access to their driveways at all times, however temporary closure of residential driveways will be required during the pouring of new curbs and sidewalks.

Oakville Transit Route 15 buses will also be re-routed to the detour route

The project includes:

  • Reconstruction and urbanization of the existing roadway including removal of roadside swales and driveway culverts
  • Full asphalt and granular replacement
  • New storm sewer
  • Concrete curb construction
  • Concrete sidewalk construction
  • Asphalt driveway restorations to property line
  • Top soil and sod restoration