Notice of Study Completion of the Munn’s Creek Flood Mitigation Opportunities Study

Thu, 03 Oct 2019

The Town of Oakville has completed the Munn’s Creek Flood Mitigation Opportunities Study (Upper Middle Road to the Morrison Wedgewood Driversion Channel) and the project file is now available for public review. The purpose of the study was to assess impacts from riverine flooding, assess the potential risks, and develop mitigation options. Please note that the Munn’s Creek Stabilization and Rehabilitation Study, dealing with issues related to creek erosion is still ongoing.

The recommended solution to reduce flood risk within the study area includes the replacement of existing culvert crossings with larger span structures, once the culverts have reached their end of service life.

The structures recommended for upgrades include:

  • McCraney Street West culvert
  • Miller Road culvert
  • Oakdale Drive to Onslow Court pedestrian culvert crossing

The recommended culvert upgrades will also be designed to improve fish habitat and wildlife passage and enhance the ecological function of the Munn’s Creek corridor.

The study was carried out in accordance with the requirements as described in the Municipal Engineers Association’s Municipal Class Environmental Assessment (EA) document (October 2000, as amended in 2015), which is approved under the Ontario Environmental Assessment Act. The Class EA process included consultation with regulatory agencies, stakeholders and the public, including two Public Information Centres that were held during the study. The recommended solution incorporates public, local municipal and agency comments received during the course of the study.

Project File now available for public review

The project file has been prepared to document the planning and decision-making process for this study. By this notice, the project file is being placed on the public record for a 30 day review period from and including October 3 to November 1, 2019 on the town’s Flood Mitigation Opportunities Study for Munn's Creek page and at the following location:

Town Hall, ServiceOakville and Clerks departments
1225 Trafalgar Road, Oakville, Ontario
Monday to Friday, 8:30 a.m. to 4:30 p.m.

Interested persons may provide written comments to one of the Project Team members listed below:

Diana Friesen, B.Sc., C.E.T., Town of Oakville
905-845-6601, ext. 3904 (TTY 905-338-4200)
diana.friesen@oakville.ca

Roger Phillips, PhD, P.Geo., Environmental Geoscientist
Aquafor Beech Limited, 905-629-0099, ext. 235
phillips.r@aquaforbeech.com

If concerns regarding this project cannot be resolved in discussions with the Town of Oakville, a person or party may request the Minister of the Ministry of the Environment, Conservation and Parks (MECP) to make an order (referred to as a Part II Order) for the project to comply with Part II of the Environmental Assessment Act which requires completion of more rigorous study by way of an Individual Environmental Assessment. The written request must be received by the Minister within the 30 day review period.

The request must be copied to the Director, Environmental Approvals Branch listed below and the Project Team.

Honorable Jeff Yurek, Minister, MECP
77 Wellesley Street West, 11th Floor
Toronto, Ontario, M7A 2T5
minister.mecp@ontario.ca

Director, Environmental Assessment and Permissions Branch, MECP
135 St. Clair Avenue West, 1st Floor
Toronto, Ontario, M4V 1P5
enviropermissions@ontario.ca