Podium - 77 East Street

A Construction Management Plan for a 10-storey apartment building with commercial space.

Project description

This Construction Management Plan outlines the construction of 77 East Street, located on the southeast corner of Lakeshore Road and East Street.

The proposed development consists of a 10-storey apartment building with ground floor commercial.

The primary use of the building will be residential with commercial retail and amenity at grade.

77 East Street Construction Activity Map

Key details

  • Site plan approved December 13, 2023
  • CMP approved December 13, 2023
  • Road Permit was issued for lane shift for East Street from Marine Drive to Lakeshore Road West including occupation of boulevard and road surface 
    • Lane shift began on March 8, 2024; to remain for the remainder of 2024. Both directions (north and south) of travel is maintained.
    • Sidewalk closed on east side. Detour is on the west side of East Street.
    • No impact on Lakeshore Road for 2024
  • Excavation began end of January 2024
  • Project scheduled to be completed in Spring 2028
  • Parking by the contractor is not required at this time, under the first phase of development

Timeline

  • October 2023 to June 2024 - Early works
  • July 2024 to March 2026 - Structure
  • April 2026 to April 2027 - Cladding/interiors
  • January 2027 to April 2027 - Landscaping
  • April 2027 - Occupancy

Questions or concerns

Businesses and residents are encouraged to reach out to the developer with any questions and concerns. If the developer is unable to help you, please contact ServiceOakville at service@oakville.ca who will ensure your request is forwarded to the appropriate department.

For concerns relating to parking, excessive noise, or construction dust, please submit a request through our Online Services 24 hours a day, days a week.