About this project
We’re making important upgrades to improve accessibility and enhance the visitor experience at Falgarwood Pool. To avoid any impact on programming, all work is scheduled during the facility’s seasonal closure.
Location
1349 Gainsborough Drive, Oakville, ON L6H 2H7
Ward 6
Project timeline
Phase one: Late November 2025 to early May 2026
Upgrades in and around the building will include:
- Accessible walkway
- New accessible service counter
- Upgraded changerooms with accessibility features
Falgarwood Pool is scheduled to reopen for regular summer programming in May 2026.
Phase two: Late September 2026 to December 2026
Outdoor enhancements will include:
- Outdoor showers, including an accessible shower
- New poured concrete deck with integrated accessible features
Impact on users
To avoid any impact on programming, all work is scheduled during the facility’s seasonal closure.
The planned improvements underscore the Town of Oakville’s commitment to providing accessible, high-quality community facilities that meet the evolving needs of residents, ensuring Falgarwood Outdoor Pool remains a welcoming and vibrant hub for years to come.
Thank you for your patience and understanding as we work to improve the pool for our community.