Towne Square transformation continues as first phase of revitalization takes shape

Wednesday, November 18, 2026

Downtown Oakville and businesses remain open and accessible as construction heads towards planned seasonal pause

The Town of Oakville is marking a milestone in the Towne Square Revitalization Project as construction continues to advance on transforming and enhancing downtown’s central gathering place.

Since construction began on September 30, 2026, crews have made steady progress on key infrastructure improvements that support the long-term renewal of Towne Square. While favourable weather helped advance construction work, crews also encountered unexpected conditions that require concrete slab repairs to walkways and areas in front of businesses. This work must be done before the waterproofing can be installed. The Town continues to work closely with its contractor and business tenants to help advance construction and keep the project on schedule.

The Town is currently planning a construction pause starting mid-December 2026 and continuing into early 2027. Timelines may change depending on weather and construction progress. Any decisions on construction activity by the Town will prioritize maintaining safe access for businesses, residents, and visitors.

During the seasonal pause, all construction equipment, materials, and fencing will be removed from the worksite. Decorative hoarding and wayfinding signage will also be removed to create a more open environment for the holiday season. All downtown shops and restaurants will remain open and accessible.

Before the winter pause, temporary asphalt will be installed in completed areas to ensure Towne Square remains safe and accessible for residents and visitors, including those attending Downtown Oakville BIA events.

Construction is expected to resume in early 2027, weather-permitting, with work continuing through to September 2027. 

During that time, the Towne Square lawn will be closed to the public. A portion of George Street, between Lakeshore Road East and Church Street, will be closed until the end of construction to accommodate Downtown Oakville BIA and other downtown events and activities. Access to the CIBC parking lot and Municipal Lot 3 will also remain open.

For project updates and construction milestones, visit oakville.ca/towne-square. Questions about the project can be directed to ServiceOakville at service@oakville.ca or 905-845-6601.

Background

  • The Towne Square Revitalization Project will create a more welcoming, accessible, and vibrant public space in the heart of Downtown Oakville.
  • When completed, the renewed Towne Square will feature: 
  • Amphitheatre-style seating for community gatherings and events;
  • A distinctive water feature, raised planters and seating areas, new trees and enhanced landscaping, and an updated central lawn; and
  • Decorative lighting and new accessible paving throughout the space.
  • The Millennium Tower Clock in Towne Square was removed and placed in storage in early September 2026 before construction began and will be returned once construction and the project is completed.
  • On May 26, 2026, Council approved an “Optimal Phasing Plan” for the Towne Square Revitalization Project presented by Parks and Open Space staff. The plan is reflective of direct input and feedback from local businesses, community partners, and interested parties. It includes measures to reduce construction impacts, accommodate events, and keep businesses and residents informed while work is underway.
  • In October 2025, Council approved a project pause for additional public consultation with businesses and the community. Staff worked closely with local businesses, the Downtown Oakville BIA, community partners, and interested parties to better understand construction impacts to the downtown area.
  • The Town continues to work closely with local business owners, residents, and community partners during the construction period to ensure they stay informed and impacts are minimized as the work progresses.