Snow clearing update - February 25, 2026

Wednesday, February 25, 2026

Ongoing snow clearing on February 25, 2026:

  • Secondary sidewalk plowing and sanding
  • Residential road salting/sanding
  • Transit stops clearing

Completed snow clearing:

  • Primary and secondary road plowing and salting
  • Primary sidewalk plowing and salting
  • Transit terminal and Ride On-Demand hubs
  • Speers Road bike lanes

While it snows, we continuously plow the primary and secondary roads. Residential roads are started only after the snow has stopped, and there has been a minimum accumulation of 7.5 centimetres. 

We will update this page as snow clearing operations progress. For more information about our snow clearing processes, please visit the Snow Clearing page. 

To stay up-to-date on our snow clearing operation, please sign up for our e-Alerts.

Updated: 2:30 p.m. February 25, 2026.