St. Jude's Cemetery and Trafalgar Lawn Cemetery Culvert Replacements

Culverts will be replaced at the Town’s two active cemeteries, St. Jude's and Trafalgar Lawn.

The Town of Oakville has initiated the detail design to replace two corrugated steel pipe (CSP) culverts at the Town’s two active cemeteries: St. Jude’s and Trafalgar Lawn Cemetery.

St. Jude's Cemetery

Design work is currently underway to replace an approximately 135-metre-long corrugated steel pipe (CSP) culvert located directly beneath the roadway within St. Jude’s Cemetery. The existing culvert has significantly deteriorated and will be replaced with a new pipe of similar size and function to continue conveying stormwater through the cemetery.

The proposed design includes:

  • Replacing the existing CSP culvert with a high-density polyethylene (HDPE) pipe of equivalent size 
  • Installation of headwalls at both the inlet and outlet, complete with safety grates 
  • Reconstruction and repaving of cemetery roadway

Expected project timeline

  • Detailed design completion – Winter 2026
  • Construction begins – Spring 2026 (subject to weather)

Trafalgar Lawn Cemetery

Design work is currently underway to replace an existing driveway culvert that recently washed out during heavy rainfall in the summer of 2024. The culvert is located at the North Park Loop of Trafalgar Lawn Cemetery, across a tributary of Sixteen Mile Creek. 

The anticipated design will include:

  • Replacing the existing CSP culvert with a new concrete box culvert
  • Reconstructing the channel using natural design elements
  • Rehabilitating the existing stormwater outlet
  • Removing and replanting trees to accommodate the works

Due to the deteriorating condition of the existing culvert and the risk of further collapse or blockage prior to the start of construction, interim stabilization work was completed in September 2025. This included removal of the collapsed culvert and associated debris, followed by stabilization of the area using salvaged stone. These measures were undertaken to prepare the site for full culvert replacement, scheduled for summer 2027.

Expected project timeline

  • Detailed design completion – Winter/Spring 2026
  • Construction begins – Summer 2027 (subject to weather)

Contact

For more information about the project, please contact Diana Michalakos by email at diana.michalakos@oakville.ca.