About this project

As part of the Town of Oakville’s annual capital replacement program, seven of Oakville’s playgrounds are being revitalized to improve accessibility and user experience across all parks. 

Each new playground will incorporate inclusive play elements and accessible features such as playground ramps and surfacing. The scope and timeline of each project will vary, with completion of the parks occurring in 2026. 

Accessibility standards

Each of the revitalized playgrounds will align with the legislative requirements of the Accessibility for Ontarians with Disabilities Act (AODA), 2005, and the Town's commitment to continuing to improve accessibility to Town services and facilities. 

In addition to the AODA, we utilize the following design standards and guidelines:

  • Design of Public Spaces Standard for the built environment, and
  • Canadian Standards Association, CAN/CSA Z164 (Children’s Playspaces and Equipment Standard), including Annex ‘H’.

These standards and guidelines help establish a minimum accessibility requirement for all newly constructed play spaces as well as any renovations and retrofits that need to take place on existing playgrounds.

About each playground design

Location

76 Burnet Drive 

Project scope 

A new playground to be installed, with accessible paved pathways integrated into the park's design. Updates to site furnishings include new benches. There will also be several landscaping improvements that will account for the new Burnet Art Installation

Project status

Design of the playground area is underway. 

Open the Burnet Park Playground Design Renderings

Location

1415 Third Line 

Project scope

New playground complete with rubberized surfacing. Pathway updates will include improvements to grading to increase accessibility to the playground and park amenities. Updates to site furnishings include new benches, picnic tables, and shade structures to improve user experience. 

Project status

Playground equipment for the new space has been procured, and the design of the playground area and amenities is underway.

Open the Glen Abbey Park Playground Design Renderings

Location

263 Jennings Crescent  

Project scope

The playground footprint is to be moved and enlarged to minimize conflict with existing trees on site and provide a better user experience. New playground equipment to be installed. New site furnishings include accessible benches.  

Project status

New playground equipment has been procured, and construction is to start in spring 2026. Work will take approximately four weeks to complete.

Open the Jennings Park Playground Design Renderings

Location

1439 Pinery Crescent 

Project scope

Both senior and junior playgrounds will be replaced. Installation of new asphalt pathways will be provided to improve access throughout the park. New site furnishings will include accessible benches. 

Project status

New playground equipment has been procured, and construction will start in spring 2026. Site work shall take approximately four weeks to complete. 

Open the Pinery Park Playground Design Renderings

Location

Between 1147 and 1149 Potters Wheel Crescent 

Project scope

A new playground with an enlarged footprint will be installed. New concrete curbs and asphalt pathways will be placed to improve site accessibility. Work will also include placement of new sub-drains and pathway culverts. 

Project status

 Construction has been paused due to winter weather. This project is on track to be completed by early spring 2026.

Open the Potters Wheel Park Playground Design Renderings

Location

1225 Windrush Drive

Project scope

A new playground with enlarged footprints will be installed. New concrete curbs and asphalt pathways have been placed to improve site accessibility. Site furnishings include benches and bike racks. 

Project status

Playground and amenity construction has concluded; this project shall be completed by late winter 2026. 

Open the Windrush Park Playground Design Renderings

Location

2088 Woodgate Drive

Project scope

Both senior and junior playgrounds will be replaced. Updates to sections of unit paver pathways will be replaced with concrete to improve accessibility. 

Project status

New playground equipment has been procured, and construction will start in spring 2026. Sitework shall take approximately four weeks to complete. 

Open the Woodgate Woods Park Playground Design Renderings